Texas Property Code Chapter 56

Texas Mineral Lien Guide

A signed field ticket shows what was done. A Texas mineral lien review also ties the work to the lease, well, pipeline, mine or quarry and identifies the company that hired you.

Texas Property Code Chapter 56

Mineral Lien Deadlines at a Glance

Notice10 days before filingMineral subcontractors

Serve written notice on the mineral property owner at least 10 days before filing the affidavit.

§§ 56.021, 56.023
Lien filing6 monthsAfter the debt accrues

Count from statutory accrual. Section 56.005 uses different rules for day or week labor and for materials or services.

§§ 56.005, 56.021
EnforcementGenerally 1 yearConfirm the filing cutoff

Section 56.041 adopts Chapter 53’s foreclosure timing. Confirm the applicable last permitted filing day and any exception with counsel.

§ 56.041 and § 53.158
Detailed notice and deadline rules

Who gets notice and when. A mineral subcontractor must serve written notice on the mineral property owner at least 10 days before filing the lien affidavit. The notice identifies the claimed amount, the company or person who owes it and the property. This lead time falls inside the filing window.

Filing and enforcement. File within six months after the indebtedness accrues. Section 56.005 ties accrual for materials or services to the last furnishing, subject to its rules for related work and gaps, and uses weekly accrual for labor performed by the day or week. Section 56.041 borrows Chapter 53’s enforcement timing and procedure. Have counsel calculate the foreclosure deadline using the applicable statutes and facts.

Who Qualifies

Chapter 56 covers qualifying mineral contractors and subcontractors that perform labor or furnish or haul materials, machinery or supplies used in mineral activities. The definition includes work on oil, gas or water wells, oil or gas pipelines, mines and quarries. Identify your customer and the mineral property owner to establish your role.

What the Lien Covers

The statute lists qualifying leaseholds, wells, pipelines, rights-of-way, appurtenances and certain materials or machinery. Work or materials furnished for a leaseholder leave the underlying fee title outside the lien under § 56.003(b).

What to Send for Review

For Permian Basin field tickets, include the operator, well or lease name, API well number when available, ticket dates, signed approvals and the entity named on each PO.

Texas Mineral Lien Questions

Whose name belongs in the notice?

The Texas statute calls for the name of the party that owes the subcontractor and a description of the applicable property. Bring the PO, signed tickets and available ownership information so counsel can identify the correct parties.

Who handles lien preparation and enforcement?

Independent licensed counsel provides legal advice and handles lien preparation, filing and enforcement. Brillman, Schultz & Associates reviews and pursues unpaid commercial accounts.

Pursue Your Unpaid Texas Oilfield Account.

Send your balance, contract or purchase order and signed job records for a confidential commercial claim review.

General information for commercial creditors. Brillman, Schultz & Associates is a commercial collection agency. Independent licensed counsel provides legal advice and handles lien preparation, filing and enforcement. A claim review request leaves statutory deadlines running.
Statutory sources checked November 16, 2026.