42 O.S. §§ 144–146 and 172
Oklahoma Oil and Gas Lien Guide
When a completion contractor has not paid for tools, supplies or crew time, trace the unpaid work to the well and the leasehold that authorized it.
42 O.S. §§ 144–146 and 172
Mineral Lien Deadlines at a Glance
The county clerk mails the owner notice under § 143.1. Separate delivery to the purchaser applies to a claim against oil or gas proceeds.
42 O.S. §§ 143.1, 144.1, 146Use the last qualifying furnishing, work or service under the relevant contract or subcontract.
42 O.S. § 146Bring the civil action within one year after filing the lien with the county clerk.
42 O.S. § 172Detailed notice and deadline rules
Who gets notice and when. Section 146 exempts these oil and gas well liens from the general construction pre-lien notice in § 142.6. The county clerk mails the notice of lien after filing under § 143.1. An oil or gas purchaser needs a copy of the lien statement under § 144.1 before the lien is effective against that purchaser.
Filing and enforcement. Section 146 sets 180 days from the last qualifying labor, service or furnishing under the relevant contract or subcontract for the filing. Section 172 generally requires suit within one year after filing with the county clerk.
Who Qualifies
Sections 144 and 145 address qualifying services, labor, materials, machinery and well supplies furnished by direct contractors and eligible subcontractors or suppliers. Section 144 also covers certain professional services and names oil and gas pipelines in the circumstances it specifies.
What the Lien Covers
Eligible collateral includes the relevant leasehold or working interest and specified wells, fixtures, equipment or qualifying proceeds. Section 146 limits the interests in the real property affected. A claim against production proceeds carries further rules.
What to Send for Review
Include the customer’s legal name, the operator, well and county, service dates, signed tickets, equipment serial numbers and the contract tying the balance to the well.
Oklahoma Mineral Lien Questions
Does Oklahoma’s 75-day construction notice apply to an oil and gas well lien?
Section 146 expressly exempts liens under §§ 144 and 145 from § 142.6. Review the contract and job scope to identify the correct statute before relying on that exemption.
Who handles lien preparation and enforcement?
Independent licensed counsel provides legal advice and handles lien preparation, filing and enforcement. Brillman, Schultz & Associates reviews and pursues unpaid commercial accounts.
Pursue Your Unpaid Oklahoma Oilfield Account.
Send your balance, contract or purchase order and signed job records for a confidential commercial claim review.
Statutory sources checked November 16, 2026.