Colorado Mechanics Lien Deadlines & Payment Bond Claims
Understand the payment timelines. Discuss the unpaid account. Start with the project setting and your place in the contracting chain below.
Colorado notice, lien filing & enforcement deadlines.
Choose the setting. Each period below includes its starting event and key conditions.
Prime / Original Contractor
10 DAYS BEFORE FILING
Owner/contractor intent notice and proof remain separate from recording. Confirm statutory recipients and use authorized personal or registered/certified-mail service. §38-22-109(3).
Statutory reference ↗Filing period
Day or piece laborers 2 months after completion of the improvement; all other claimants 4 months after that claimant's last labor or materials
Lawsuit period
6 months from last work or completion, not from recording, plus a recorded notice of commencement of action
Subcontractors & Suppliers
10 DAYS BEFORE FILING
Serve owner/agent and prime/agent at least 10 days before recording by statutory service, with required proof filed with the lien. §38-22-109(3).
Statutory reference ↗Filing period
Day or piece laborers 2 months after completion of the improvement; all other claimants 4 months after that claimant's last labor or materials
Lawsuit period
6 months from last work or completion, not from recording, plus a recorded notice of commencement of action
Lower-Tier Claimants
10 DAYS BEFORE FILING
Serve owner/agent and prime/agent at least 10 days before recording by statutory service, with required proof filed with the lien. §38-22-109(3).
Statutory reference ↗Filing period
Day or piece laborers 2 months after completion of the improvement; all other claimants 4 months after that claimant's last labor or materials
Lawsuit period
6 months from last work or completion, not from recording, plus a recorded notice of commencement of action
Colorado public-project overview · Prime Contractor
Review the public contract
Contractual notices, approvals, pay applications, retainage, and dispute procedures require an individual review.
Contract-based claim
A prime contractor’s payment dispute with a public owner differs from a downstream claimant’s payment-bond claim.
Counsel must assess
The agreement, governing law, project type, and remedy determine the applicable process and deadline.
Direct Subcontractors & Suppliers
IDENTIFY THE STATUTORY ROUTE
Public-bond actions and withheld-fund claims have separate conditions. Confirm the bond, awarding entity, completion, and final-settlement records.
Statutory reference ↗BY FINAL SETTLEMENT
A verified unpaid-claim statement may be filed with awarding body through final settlement to invoke withholding protection. §38-26-107.
Statutory reference ↗6 MONTHS / 90 DAYS
Section 38-26-105 uses six months after work completion for its action. Section 38-26-107 provides a separate 90-day final-settlement process. Counsel must identify the applicable route.
Statutory reference ↗Lower-Tier Claimants
IDENTIFY THE STATUTORY ROUTE
Public-bond actions and withheld-fund claims have separate conditions. Confirm the bond, awarding entity, completion, and final-settlement records.
Statutory reference ↗BY FINAL SETTLEMENT
A verified unpaid-claim statement may be filed with awarding body through final settlement to invoke withholding protection. §38-26-107.
Statutory reference ↗6 MONTHS / 90 DAYS
Section 38-26-105 uses six months after work completion for its action. Section 38-26-107 provides a separate 90-day final-settlement process. Counsel must identify the applicable route.
Statutory reference ↗Already filed a lien. Still unpaid?
A lien does not collect the money by itself. Payment discussions may still involve disputed work, change orders, retainage, or a customer that stopped responding.
Review the unpaid balance →Concerned about a legal deadline?
Contact independent Colorado construction counsel promptly. Do not wait for a BSA review before obtaining legal help.
Return to the timing overview ↑A practical starting point for collection.
You do not need to sort out every legal issue before organizing the receivable.
Tell us what is owed.
Identify your customer, the project, outstanding amount, and how long payment has been overdue.
Show the account record.
Share agreements, invoices, supporting job records, and the customer’s response.
Discuss a recovery approach.
We can discuss collection options. Legal advice and lien or bond work belong with independent counsel.
- Contract, purchase order, and change orders
- Invoices, aging report, and payment history
- Delivery tickets and evidence of completed work
- Dispute emails and payment commitments
- Project owner, contractor, and customer details
- Existing notices, bonds, filings, or legal correspondence
Before you take the next step.
Does BSA prepare or file mechanics liens or bond claims?
No. BSA handles commercial debt recovery. Independent licensed counsel evaluates and performs lien, bond, notice, and court work.
Can I discuss an account if I never filed a lien?
Yes. The underlying contract claim may still warrant collection review even if no lien was filed. Counsel must evaluate legal rights and deadlines.
Does submitting a review request protect a deadline?
No. A BSA review does not preserve rights, stop time, or replace a required notice, filing, or lawsuit.
Let’s review the unpaid account.
Tell us who owes you, where the project is located, what remains unpaid, and what notices or bond information you already have.
Start My Free Claim Review →Colorado private-work reference: C.R.S. §§ 38-22-109(4), 38-22-109(5), 38-22-110. Public-work reference: Colo. Rev. Stat. § 38-26-105. Federal reference: 40 U.S.C. §§ 3131–3133.
General educational information for commercial construction accounts, not legal advice or a deadline calculator. BSA does not calculate or monitor deadlines, file liens or bond claims, or guarantee recovery. Content reviewed November 5, 2026.