K.S.A. §§ 55-207 through 55-215

Kansas Oilfield Lien Guide

A Kansas leasehold invoice and a bill for hauling someone else’s oilfield equipment raise different filing questions. Identify the exact service and the property you seek to reach.

K.S.A. §§ 55-207 through 55-215

Mineral Lien Deadlines at a Glance

Oil and gas leasehold lien

NoticeMechanics lien procedureCheck service for your role

The leasehold notice statute incorporates the mechanics lien procedures.

K.S.A. § 55-210
Lien filing6 monthsAfter the last qualifying item

Count from the last qualifying material or labor under the contract.

K.S.A. § 55-209
EnforcementGenerally 1 yearAfter filing

The incorporated procedure generally measures from filing, with a separate rule for certain promissory notes.

K.S.A. §§ 55-210, 60-1105

Oilfield equipment hauler lien

NoticeAt filingSend a copy to the equipment owner

Serve the owner or authorized representative by registered mail at the time of filing.

K.S.A. § 55-214
Lien filing120 daysAfter transport and delivery

File in the county where the oilfield equipment was delivered.

K.S.A. § 55-214
Enforcement6 monthsSeparate hauler action period

Section 55-215 provides six months for a specified action. Confirm the applicable start date with counsel.

K.S.A. § 55-215
Detailed notice and deadline rules

Who gets notice and when. Section 55-210 incorporates mechanics-lien notice procedures for eligible leasehold claims. Section 55-214 requires the equipment hauler to serve a copy on the equipment owner or authorized representative by registered mail at the time of filing.

Filing and enforcement. Section 55-209 provides six months from the last qualifying work or furnishing under the contract for the covered leasehold lien statement. Section 55-210 directs enforcement to the mechanics-lien procedure, which generally gives one year from filing under § 60-1105. The separate hauler lien has a 120-day filing rule from transport and delivery and a six-month action rule in § 55-215.

Who Qualifies

Sections 55-207 and 55-208 apply to qualifying labor or equipment, machinery and supplies for oil and gas leaseholds or pipelines. Section 55-213 separately covers qualifying transport under an express contract with a party listed in the statute.

What the Lien Covers

A qualifying labor or supply lien can reach the affected oil or gas leasehold or pipeline and property listed in § 55-207. The special hauler lien reaches the equipment owner’s interest in the equipment hauled.

What to Send for Review

For a haul, send the express contract or written order, actual equipment owner, pickup and delivery locations, signed delivery ticket, serial numbers and the date delivered.

Kansas Mineral Lien Questions

Does the six-month leasehold filing rule apply to an equipment hauler’s lien?

The separate hauler statute sets a 120-day filing period and calls for service at filing. Bring the transport contract and delivery record so counsel can identify which remedy applies.

Who handles lien preparation and enforcement?

Independent licensed counsel provides legal advice and handles lien preparation, filing and enforcement. Brillman, Schultz & Associates reviews and pursues unpaid commercial accounts.

Pursue Your Unpaid Kansas Oilfield Account.

Send your balance, contract or purchase order and signed job records for a confidential commercial claim review.

General information for commercial creditors. Brillman, Schultz & Associates is a commercial collection agency. Independent licensed counsel provides legal advice and handles lien preparation, filing and enforcement. A claim review request leaves statutory deadlines running.
Statutory sources checked November 16, 2026.