Texas notice, lien filing & enforcement deadlines.

Choose the project and your role. Each deadline has its own trigger and required recipients.

Original / Prime Contractor

Preliminary notice

NO §53.056 NOTICE

Direct owner contract

The monthly unpaid-balance notice in §53.056 applies to claimants other than original contractors. Affidavit filing and post-filing notice remain separate requirements.

§§53.052–53.056 ↗
Mechanics lien

15TH · 4TH MONTH

File the lien affidavit

After the month your work was completed, terminated, or abandoned. File with the county clerk where the property is located.Send the owner a copy within 5 days after filing.

§§53.052, 53.055 ↗
Enforcement

1 YEAR

Foreclosure lawsuit

Measured from the last permitted affidavit-filing day, rather than the day you actually filed. A qualifying written, recorded extension requires separate legal review.

§53.158 ↗
Commercial, nonresidential projects. These summaries use the framework for original contracts entered on or after January 1, 2022. Retainage has separate notice and filing rules; private payment bonds also require a separate review. Obtain independent filing or legal help while time remains.

A claim is already on record

Already filed a lien. Still unpaid?

A lien does not collect the money by itself. Payment discussions may still involve disputed work, change orders, retainage, or a customer that stopped responding.

Review the unpaid balance →
Time may be running

Concerned about a legal deadline?

Contact independent Texas construction counsel promptly. Do not wait for a BSA review before obtaining legal help.

Return to the timing overview ↑

Move the account forward

A practical starting point for collection.

You do not need to sort out every legal issue before organizing the receivable.

01

Tell us what is owed.

Identify your customer, the project, outstanding amount, and how long payment has been overdue.

02

Show the account record.

Share agreements, invoices, supporting job records, and the customer’s response.

03

Discuss a recovery approach.

We can discuss collection options. Legal advice and lien or bond work belong with independent counsel.

  • Contract, purchase order, and change orders
  • Invoices, aging report, and payment history
  • Delivery tickets and evidence of completed work
  • Dispute emails and payment commitments
  • Project owner, contractor, and customer details
  • Existing notices, bonds, filings, or legal correspondence

Common questions

Before you take the next step.

Does BSA prepare or file mechanics liens or bond claims?

No. BSA handles commercial debt recovery. Independent licensed counsel evaluates and performs lien, bond, notice, and court work.

Can I discuss an account if I never filed a lien?

Yes. The underlying contract claim may still warrant collection review even if no lien was filed. Counsel must evaluate legal rights and deadlines.

Does submitting a review request protect a deadline?

No. A BSA review does not preserve rights, stop time, or replace a required notice, filing, or lawsuit.


Your work deserves a payment conversation

Let’s review the unpaid account.

Tell us who owes you, where the project is located, what remains unpaid, and what notices or bond information you already have.

Start My Free Claim Review →

Texas private-work reference: Tex. Prop. Code §§ 53.003, 53.052–53.057, 53.158. Public-work reference: Tex. Gov't Code ch. 2253. Federal reference: 40 U.S.C. §§ 3131–3133.

General educational information for commercial construction accounts, not legal advice or a deadline calculator. BSA does not calculate or monitor deadlines, file liens or bond claims, or guarantee recovery. Content reviewed November 5, 2026.